HRA 03/31/1983 SPEC - 29375SPECIAL
HOUSIl93, & REDEVELOPMENT AUTEURITY
MEETING
MARCH 31, 1983
CALL TO ORDER:
Chairperson Caamers called the March 31, 1983, Special Housing & Redevelopment
Authority meeting to order at 5:00 p.m.
ROLL CALL:
Members Present: Larry Canmers, Carolyn Svendsen, Elmars Prieditis
Members Absent: Walter Rasmussen, Duane Prairie
Others Present: Jerrold Boardman, Executive Director HRA
Nasim M. Qureshi, City Manager
William J. Nee, Mayor
Edward Fitzpatrick, Councilman
Edward Hamernik, Councilman
Mark Burch, Assistant Public Works Director
John Flora, Public Works Director
Sid Inman, Director of Central Services
Harold Skjelvostad - InterDesign, Site Planner /Landscape
Architect.
Jerrold Boardman - Executive Director HRA submitted the bid tabulation sheet
for the Center City Plaza and Phase II Project.
Mr. Qureshi, City Manager, asked for some indication fran the HRA on which bid
along with modification is acceptable to HRA and he would like to present then
to the City Council at the April 4, 1983 Council meeting.
Mr. Canmers questioned this procedure and asked why it must be sent to the
Council.
Mr. Qureshi explained that this is required of the City Council because the
HRA requested the City to assess the project. The City Council is the one who
calls for bids and will be awarding then. He explained that it is the purpose
of the staff to take the information and choices made by HRA to the City
Council directly before awarding the bids. The HRA cannot call for and award
bids unless they want to pay for a project directly and not use the special
assessment procedure.
Mr. Qureshi explained there are four elements involved in the development.
They are: the parking lots (Civic Center and Office Building) 64th street
realignments, water and sewer for the Office Building and the Plaza
Development.
Mr. Qureshi stated that in January of 1983, it was requested the City Council
go ahead with the Parking Lot, 64th Street realignments and the Water and
Sewer Bids. The numbers were sent to the HRA and they were comfortable with
the numbers.
Mr. Qureshi stated the Architect initially estimated the project costs in
January 1983. The costs were then given to the HRA for their confirmation and
got go ahead for the project bidding. The bid proposal request was layed out
with base bid along with number of different alternates so that the HRA can
pick and choose depending upon the bid cost and the amount of money budgeted
so the HRA can get the best type of facility for the money.
Mr. Mark Burch, Assistant Public Works Director, explained the different parts
of the bid. Base bid included:
Mark explained the base bids and the alternates for the Plaza: Alternative
A -1 is for the fountains; A -2 is for the irrigation with plastic heads; A -3 is
for irrigation with brass head; A -4 is to provide sleeving for irrigation; &-1
is to install wall lights; B-2 is for the Plaza lights with trash receptacles;
B-3 alternate Plaza lights and B-6 is the electrical service connections. It
was recommended that they award the base bid with the following alternates:
A -1, A -3, Br-1, B-4, &-5 and B-6.
The base bid included the landscaping f or the Plaza area. They are,
Alternative 1 for the Landscaping for the office building, Alternate 2 is the
landscaping for the 5th Street island, Alternate 3 is the landscaping for the
Clinic and Alternate 4 is for the 5th Street boulevard.
Mr. Qureshi stated the costs came in much too high when the bids were
received. The fountains were estimated at $20,000 by the Architect but came
• in at $87,000. The electrical was estimated at $20,000 and came in at
$40,000.
Mr. Qureshi explained how alternative material could be used in the
construction of the fountains, such as changing the type of aluminum in order
to bring the cost down.
Mr. Qureshi stated there are alternatives and certain choices available to you
for you to make determinations.
Mr. Qureshi went over the project costs and bids for the HRA. Plans were
submitted for their review during the discussion. The items that were
discussed were the fountains, irrigation, wall lights, pylon lights, overhead
lights and electrical service. The following alternates were recommended,
bringing the alternates cost to a total of $163,960.
Alternate A -1
Fountains
$87,000.00
Alternate A -3
Irrigation
18,600.00
Alternate B-1
Wall Lights
16,740.00
Alternate B-4
Pylon Lights
3,000.00
Alternate Br5
Overhead Lights
35,595.00
Alternate Br6
Electric Service
3.025.00
$163,960.00
I
r ]
Mr. Ccnwers stated that this is a substantial increase.
Mr. Qureshi then explained the landscaping bids.
He felt that cuts should be made, however, those cuts should not destroy the
integrity of the Plaza. He explained sane of the possible reductions: 1) 1
flag instead of 2, 2) delete some unnecessary walls, 3) eliminate recessed
lights and provide satisfactory replacement lights and 4) eliminate 1 planter
but leave shrubs. These reductions cane to a total of $61,551.
Mr. Commers asked what is the "cost to the others "?
Mr. Qureshi stated that those costs relate to the work around the office
building, the clinic and the work on 5th Street.
Mr. Qureshi stated that the alternatives with the base bid is the total cost
for the whole project. These costs are then broken down and allocated to the
specific items (like the office building, the parking lots, 5th Street and the
Plaza).
Mr. Qureshi stated that the office building and Civic Center parking lot was
$140,000 and would be assessed to the HRA. This would include the paving,
lights and irrigation related to that property.
Mr. Commers stated that the initial cost of the parking lot was for $140,000
but he was not aware that this included anything more than the paving.
Mr. Qureshi stated the bids for the
similar Paving were let separately because all
project items should be handled by the contractor best able to give a
good product.
Mr. Boardman stated the plaza and the parking lot and street bids were let
separately as was the landscaping. This saves the HRA a lot by combining
similar items in one bid.
Mr. Prieditis questioned the Alternative B -1 bid for the wall lights. He
asked if the recessed lights would be deleted and if they are recessed in the
concrete and if there would be a credit.
Mr. Burch stated that the concrete is fix and form and that the additional
concrete work is included in the light bid.
Mr. Qureshi suggested that the HRA members see the sheet regarding the
possible deletions on the Plaza. He stated that a change order in the
contract for $61,000 would be necessary if you want to award the base bid to
came within the guidelines.
Mr. Commers asked about the difference in fountains.
Mr. Qureshi stated that the fountain is the highest area of cost discrepancy.
The problem is the increase from the Architect's estimate of $20,000 to the
. actual bid cost of $87,000.
HOUSING AND REDEVELOPMENT AUTHORITY MEETIMI, MARCH 31, 1983 PAGE 4
jft Mr. Qureshi said that they were given a price from the Architect's estimate of
the Plaza. This information was given to you in January.
Mr. Commers stated his principal concern is about meeting the numbers and
making sure that the HRA cash flow is adequate for the development in the
area.
Mr. Qureshi stated the costs of the Plaza with the suggested cuts and other
contributions is $248,000. If you add in the contingency and finance costs,
the project will be below $300,000 and would fall within the BRA budget.
Mr. Qureshi stated there are two ways of doing it; 1) the HRA can choose to
pay up front for the project or 2) the City can loan the money and have it
then assessed to the HRA.
Mr. Commers asked Sid what does that do to the HRA cash flow,
Mr. Inman stated that it does not change the expense for the first twelve (12)
months but reduces future assessment payments.
Mr. Prieditis asked about the lack of contingency.
Mr. Qureshi stated $52,000 include contingency and interest during
construction, etc., is built into that $300,000 figure,
• Mr. Conmers asked that if the HRA is assessed for the plaza costs that $52,000
is for interest and carrying costs and other contingency.
Mr. Qureshi stated that this would be the cost if the HRA wants the assessment
and the City finances the HRA during construction.
Mr. Commers asked Mr. Iimian to give them some numbers on the effects of an
outright payment for the plaza. More specifically, the effect of direct
payment in 1984 & 1985.
Mr. Inman stated that the original effect obviously would be to reduce the
mount of cash available by $300,000. This would reduce the HRA's ability to
earn interest at the same rate that the City would charge to loan that money.
Therefore, the first twelve (12) months would cost the HRA just about the same
irrespective of whether they were assessed or pay up front, From that point
on, the immediate effect would be in the inability of the HRA to invest the
$300,000, which would be offset by the additional assessment payment they
would not be making. For the first two to three years the HRA would be behind
in actual cash flow and after four years could potentially gain. It would
really depend on the interest rate and the time.
Mr. Carriers asked what the cash savings are and how badly does that hurt our
cash flow over 15 years.
r-7
LOA
Mr. Qureshi asked Mr. Inman to coarse up with an estimate within the next ten
minutes.
Mr. Skjelvostad then explained the changes in the materials and design for the
fountain and the sun dial. He explained the bids came in high. The bids from
the contractor could be reduced by building 7 fountains instead of 9 saving
$28,000, and by changing the number to five and the material they could save
$30,000.
Mr. Qureshi stated the reduction in number and having the same shape and use a
different aluminum, with the hope that enough money can be saved to have at
least seven structures.
Mr. Boardman stated that each option saves money.
Mr. Prieditis stated he would like to make sure no reflective, sound bouncing
off the aluminum or whistling would occur.
Mr. Cammers stated he is concerned with the maintenance of it in regards to
the Public Works Department.
Mr. Skjelvostad explained there should be no change as far as maintenance is
concerned. He also explained that it is more reflective but not much.
Mr. Prieditis stated he would like to maintain the numbers if possible. He
would like to see a material change with the initial design.
Mr. Qureshi stated another item was the deletion of the wall lights with a
replacement of overhead lighting. This could reduce the bid by $20,000. They
are nice to have but the bid costs came in too high.
Mr. Commers stated that the carrying cost was never given to them. They
thought that they were talking about a total cost of $300,000.
Mr. Qureshi stated $30,000 would be the City's financing costs.
Mr. Qureshi stated he wanted to make it clear that the construction costs for
the Plaza came in at $300,000. That means that the total costs to be assessed
to the HRA would be approximately $3601,000. If the HRA wants to bring the
total costs under the $3001,000 figure, cuts would have to be made. If the HRA
wants to pay the Plaza costs directly there would be a savings to the HRA
regarding the carrying costs.
Mr. Qureshi asked in what areas does the HRA want to make adjustments to and
what guidelines do you want to give the City Council to aid them in awarding
the contract.
Mr. Com-iers asked Mr. Inman if he has had cash flow projects yet.
0
HOUSING AND RIDEVEIAPMENT AUTHORITY MEETING, MARCH 31, 1983 PAGFy 6
Mr. Imnan stated that the information that he would give them now was rough
and that he would have to run it on the computer to be absolutely accurate.
Generally speaking, at the end of 1983, the HRA would be approximately
$450,000 less in their cash flow position than they would be if they did not
pay the assessment up front. He further stated that at the end of 1984, they
would only be approximately $160,000 behind the difference being the $300,000
they paid up front plus the loss of interest along with the assessment payment
they would not be making in October and the additional interest they would
earn on that.
Mr. Commers asked Mr. Inman what the effect would be on his worst case model
and Mr. Inman stated that the worst case model included no interest income
anyway. Therefore, reducing the cash balance by $300,000 would not effect the
worst case model.
Mr. Burch showed brochures of the different types of lights.
Mr. Qureshi stated that they should try to make rational changes. Tied to the
guidelines as we feel the plaza will be used mainly in the summer time. That
it is your choice if you want it assessed.
Mr. Prieditis stated he preferred the recessed lighting over the other.
Mr. Skjelvostad stated it is costly to add lights.
Mr. Qureshi stated before the base bid is brought to the City Council,
alternatives should be presented for approval. This should be done before we
sign the document and award the bids.
MOTION BY MR. PRIEDITIS, SECONDED BY MS. SVENDSEN, TO PAY THE $300,000 UP
FRONT FOR THE PLAZA WITH NO ASSESSMENTS AND TO INCLUDE AS MANY ITEMS AS
POSSIBLE SUCH AS RECESSED LIGHTING AND THE FOUNTAIN, ETC.
UPON A VOICE VOTE, ALL VOTING AYE, CHAIRPERSON COMMERS DECLARED THE MOTION
CARRIED UNANIMOUSLY.
MOTION BY MR. PRIEDITIS, SECONDED BY MS, SVENDSEN, TO RECOMMEND TO THE COUNCIL
TO AWARD THE BID TO MONETTE CONSTRUCTION WITH ALTERNATIVES A1, A3, B1, B4, B5
AND B6.
UPON A VOICE VOTE, ALL VOTING AYE, CHAIRPERSON COMMERS DECLARED THE MOTION
CARRIED UNANIMOUSLY.
MOTION BY MR. PREIDITIS, SECONDED BY MS. SVENDSEN, TO AWARD THE BID TO NOBLE
NURSERY WITH THE UNDERSTANDING THAT $23,137.50 WILL BE CHARGED AGAINST THE
PLAZA.
UPON A VOICE VOTE, ALL VOTING AYE, CHAIRPERSON COMMERS DECLARED THE MOTION
CARRIED UNANIMOUSLY.
MOTION BY MR. PREIDITIS, SECONDED BY MS, SVENDSEN, TO ADJOURN THE MEETING.
UPON A VOICE VOTE, ALL VOTING AYE, CHAIRPERSON COMMERS DECLARED gIE MARCH 311
1983 HOUSING AND REDEVELOPMENT AUrIHORITY MEETING ADJOURNED AT 7:08 P.M.
0