RES 1984-51 - 0000539275
RESOLUTION NO. 51 - 1984
RESOLUTION ORDERING IMPROVEMENT AND APPROM OF PLANS AND
ORDERING ADVERTISEMENT FOR BIDS: STREET IMPROVEMENT
PROJECT NO. ST. 1984 -1 & 2 (ADDENDUM #2)
WHEREAS, Resolution No. 43 - 1984 adopted on the 26th day of March, 1984, by
the City Council, set the date for hearing on the proposed improvements as
specifically noted in the Notice of Hearing attached thereto for reference as
Exhibits "A ", and,
WHEREAS, all of the property owners whose property is liable to be assessed
with the making of these improvements (as noted in said notice) were given ten
(10) days notice by mail and published notice of the Council Hearing through
two (2) weekly publications of the required notice, and the hearings were held
and the property owners heard thereon at the hearing as noted in said notice:
and
WHEREAS, Resolution No. 50 - 1984 adopted by the City Council of the City of
Fridley ordered all of these improvements.
NOW, THEREFORE, BE IT RESCLVED by the City Council of the City of Fridley,
Anoka County, Minnesota as follows:
1. That the following improvements proposed by Council Resolution No. 42 -1984
are hereby ordered to be effected and completed as soon as reasonably
possible, to-wit:
Street Improvements, including grading, stablilized base, hot -mix
bituminous mat, concrete curb and gutter, sidewalks, storm sewer
system and other facilities located as follows:
66th Avenue
Creek Park Lane
Ctrl. De Sac to Arthur Street
Central Avenue to Arthur Street
That the work involved in said improvements as listed above shall hereinafter
be included as part of:
h "IDIW a 104*1�41fj a ID, •,• ra nff
2. The plans and specifications prepared by the Public Works Director for
such improvements and each of them pursuant to the Council resolutions
heretofore adopted, a copy of which plans and specifications are hereto
attached and made a part thereof, are hereby approved and shall be filed with
the City Clerk.
The Public works Director shall accordingly prepare and cause to be inserted
in the official newspaper advertisements for bids upon the making of such
improvements under such approved plans and specifications. The advertisement
shall be published for three (3) weeks (at least 21 days) , and shall specify
the work to be done and will state that bids will be opened and considered at
Page 2 — Resolution No. 51 - 1984 G
11:00 a.m. on the 1st day of May 1984 in the Council Chambers of the City Hall
and that no bids will be considered unless sealed and filed with the Public
s't bid bond or certified check
d accompanied a cash de i �
an accom i
Works Director pan by po
payable to the City for five percent (5%) of the amount of such bid. That the
advertisement for bids for STREET IMPROVEMENT ST. 1984 -1 & 2 shall be
substantially in the standard form.
PASSED AND ADOPTED BY THE CITY COUNCIL OF THE CITY OF FRIDLEY THIS 16TH DAY OF
APRILr 1984.
V �
WILLIAM J. NE -MAYOR
ATTEST:
SIDNEY C. INMAN - CITY CLERK
r
11
Page 3 — Resolution No. 51 - 1984
�•� r•• a is ••• a
Sealed bids will be received and publicly opened by the City of Fridley, Anoka
County, Minnesota, at the office of the Public Works Director, 6431 University
Avenue N.E., Fridley, Minnesota 55432 (Tel. 571 -3450) on the 1st day of May, at
11:00 a.m.
12,000 Cubic Yards Common Excavation
7,000 Tons Aggregrate Base (Class V)
4,500 Tons Asphalt
250 Tons Bituminous Material for Mixture
8,600 Lineal Feet B-618 Concrete Curb and Gutter
1,200 Square Feet Brick Median Paving
All in accordance with plans and specifications prepared by John G. Flora,
P.E., Public Works Director, Fridley City Hall, 6431 University Avenue N.E.
Fridley, MN 55432 (Tel. 571 - 3450).
Plans and specifications may be examined at the office of the Public Works
Director and copies may be obtained for the Contractor's individual use by
applying to the Public Works Director and depositing with the Public Works
Director $25.00 for each set. The deposit will be refunded to each bidder
submitting a bona fide bid upon return of the documents in good condition within
ten (10) days from the bid opening date.
Bids must be made on the basis of cash payment for work, and accompanied by a
cash deposit, certified check (on a responsible bank in the State of Minnesota)
or a bidder's bond made payable without condition to the City of Fridley,
Minnesota, in an amount of not less than five (5%) per cent of the total amount
of the bid.
The City Council reserves the right to reject any and all bids and to waive any
informalities in any bids received without explanation.
No bid may be withdrawn for a period of thirty (30) days.
By order of the City Council of the City of Fridley, Minnesota.
Dated this 26th day of March, 1984.
Published: Fridley Sun
April 11
April 18
April 25
John G. Flora, P.E.
PUBLIC WORKS DIRECTOR
Construction Bulletin
April 11
April 20
April 27
77