RES 1994-53 - 00003062IRESOLUTION NO. 53 - 1994
A RESOLUTION APPROVING PLAT, P.S. #94 -03, TARGET
NORTHERN DISTRIBUTION CENTER 2ND ADDITION
WHEREAS, the Planning Commission held a public hearing on the Plat, P.S. #94-
03, on March 23, 1994, and recommended approval with stipulations; and
WHEREAS, the City Council also conducted a public hearing on the proposed Plat
at their April 18, 1994 Council meeting and approved the Plat at their July
11, 1994 meeting; and
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Fridley
hereby approves the Plat, P.S. #94 -03, Target Northern Distribution Center 2nd
Addition, with stipulations attached as Exhibit A, and authorizes the Mayor
and City Manager to sign the Plat as prepared by Sunde Land Surveying Inc.
BE IT FURTHER RESOLVED that the petitioner is requested to record this Plat at
Anoka County within six (6) months or said approval with become null and void.
o
WILLIAM A. CHAMPA - CITY LERK
PASSED AND ADOPTED
BY THE CITY COUNCIL OF THE CITY OF FRIDLEY THIS
11TH DAY OF
JULY, 1994.
WILLIAM J. NEE
MAYOR
ATTEST:
o
WILLIAM A. CHAMPA - CITY LERK
.•
I Page 2 -- Resolution No. 53 - 1994
EXHIBIT A
1. The petitioner shall submit detailed grading and drainage plans for a
trailer parking expansion, including delineation of any wetlands located
on the property prior to construction. The Planning Commission and City
Council shall review the plans if the parking area provides for more
storage than 100 trailers.
2. The petitioner shall submit a detailed bikeway and landscaping plan for
relocation of the existing bikeway adjacent to the westerly lot line of
Lot 1, Block 1, Target Northern Distribution Center 2nd Addition prior
to construction.
3.
The petitioner shall prepare, execute, and record new bikeway easement
documents and relocate the bikeway at the time of construction.
4.
A joint driveway easement shall be executed between Fridley Business
Center Partnership and Dayton Hudson regarding the easterly driveway
located on Lot 2, Block 1, Northco 4th Addition.
5.
An open air easement shall be executed and recorded against Lot 1, Block
1, Target Northern Distribution Center 2nd Addition, between Fridley
Business Center Partnership and Dayton Hudson. This open air easement
shall prevent construction of any structures within the 35 foot
'
easement.
6.
Primary truck trailer access shall be limited to the entrance on the
Central Avenue service drive with secondary access at existing Able
Street. The driveway located on Lot 2, Block 1, Northco 4th Addition
shall be used for emergency access only.
7.
Park fees shall be paid at time of building permit issuance.
8.
A special use permit application shall be submitted if it is determined
by the City that adequate screening does not exist to screen the
vehicles at time of construction.
9.
A letter of credit or performance bond shall be submitted prior to
construction in the amount of 38 of the total construction cost of the
expansion of the parking area, bikeway /walkway, and landscaping. The
bond or letter of credit will be retained for at minimum one year and
one full growing season.
10.
Existing wetlands shall not be altered, drained, or filled, including
receiving direct, unfiltered runoff from parking lot expansion.
11.
A permit from the Rice Creek Watershed District shall be obtained prior
'
12.
to construction.
A special use permit application shall be submitted if it is determined
by the City that adequate screening does not exist to screen the
vehicles at time of construction.