Res 2019-18 Final Plans ST2019-01RESOLUTION NO. 2019 - 18
RESOLUTION ORDERING FINAL PLANS, SPECIFICATIONS AND CALLING FOR
BIDS: 2019 STREET REHABILITATION PROJECT NO. ST 2019 - 01
WHEREAS, the construction of certain improvements is deemed to be in the interest of the City
of Fridley and the property owners affected thereby, and
WHEREAS, the City of Fridley has prepared a Capital Investment Program to systematically
reconstruct streets in the City regularly to maintain roadway quality and performance, and
WHEREAS, the City of Fridley's Engineering Department has completed preparation of a
feasibility report and estimates of costs thereof for the improvements, and
WHEREAS, it is the intent of the City of Fridley to fund a portion of the project costs through
special assessments to benefiting property owners in accordance with its Roadway Major
Maintenance Policy, and
WHEREAS, pursuant to direction of the City Council, a report has been prepared by the City of
Fridley Public Works Department with reference to the specific improvements, and
WHEREAS, Resolution No. 2019-08 adopted February 11, 2019 received the feasibility report
and called for a public hearing on the matter of the construction of certain improvements listed
therein, and
WHEREAS, a public hearing regarding said improvements was set for April 8, 2019, and ten
days' mailed notice and two weeks' published notice of the hearing was given, and
WHEREAS, at said hearing on improvements, the City Council heard all those persons that
desired to address the Council,
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FRIDLEY, ANOKA COUNTY, MINNESOTA:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the
feasibility report.
2. The improvements proposed in the feasibility report are hereby ordered to be
effected and completed as soon as reasonably possible, to -wit:
Street and utility improvements, including milling, bituminous asphalt overlay, pavement
reclamation, sidewalk construction, drainage, water main and utility repairs including the
street segments as follows:
Resolution No. 2019 —18
69TH AVENUE NE
Page 2
from UNIVERSITY AVE EAST SERVICE RD
TO EASTERN TERMINUS
UNIVERSITY AVE EAST SERVICE RD from T.H. 47 TO 73RD AVENUE NE
71 ST AVENUE NE from UNIVERSITY AVE EAST SERVICE RD
TO LOCKE PARKWAY
3. That the work be incorporated in the 2019 STREET REHABILITATION
PROJECT NO. ST2019-01.
4. That the work be performed under this project may be performed under one or
more contracts as may be deemed advisable upon receipt of bids.
5. That the Director of Public Works, James P. Kosluchar, P.E. is hereby
designated as the engineer for this improvement. He shall oversee the
preparation of plans, specifications and estimates of costs thereof for making of
such improvements.
6. That final plans, specifications, and estimates are prepared by the Public Works
Engineering Division and provided to the City Council as they are completed.
7. That the Engineering Division call for bids in order that project award and
construction can be considered.
PASSED AND ADOPTED BY THE CITY COUNCIL OF THE CITY OF FRIDLEY THIS
8TH DAY OF APRIL 2019.
SCOTT J. LUND — MAYOR
ATTEST:
DEBRA A. SKOGEN - CITY CLERK