Res 2019-71 Ordering Final Plans for ST2020-01
RESOLUTION NO. 2019 – 71
A RESOLUTION ORDERING FINAL PLANS, SPECIFICATIONS AND CALLING
FOR BIDS: 2020 STREET REHABILITATION PROJECT NO. ST2020-01
WHEREAS, the construction of certain improvements is deemed to be in the interest of the city
of Fridley and the property owners affected thereby, and
WHEREAS, the City of Fridley has prepared a Capital Investment Program to systematically
reconstruct streets in the City regularly to maintain roadway quality and performance, and
WHEREAS, the City of Fridley’s Engineering Department has completed preparation of a
feasibility report and estimates of costs thereof for the improvements, and
WHEREAS, it is the intent of the City of Fridley to fund a portion of the project costs through
special assessments to benefiting property owners in accordance with its Roadway Major
Maintenance Policy, and
WHEREAS, pursuant to direction of the City Council, a report has been prepared by the City
of Fridley Public Works Department with reference to the specific improvements, and
WHEREAS, on October 28, 2019 the City Council received the feasibility report and called for
a public hearing on the matter of the construction of certain improvements listed therein by
Resolution No. 2019-61, adopted October 28, 2019, and
WHEREAS, a public hearing regarding said improvements was set for November 25, 2019,
and ten days' mailed notice and two weeks' published notice of the hearing was given, and
WHEREAS, at said hearing on improvements, the City Council heard all those persons that
desired to address the Council,
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FRIDLEY, ANOKA COUNTY, MINNESOTA:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the
feasibility report.
2. The improvements proposed in the feasibility report are hereby ordered to be
effected and completed as soon as reasonably possible, to-wit:
Resolution No. 2019-71 Page 2
Street and utility improvements, including milling, bituminous asphalt overlay,
pavement reclamation, trail construction, drainage, water main and utility repairs
including the street segments as follows:
79TH WAY from EAST RIVER ROAD to CUL-DE-SAC
ASHTON AVENUE from 79TH WAY to CUL-DE-SAC
ELY STREET from 232’ WEST OF RUTH STREET to 1,041’ EAST
HUGO STREET from EAST RIVER ROAD to IRONTON STREET
IRONTON STREET from EAST RIVER ROAD to HUGO STREET
LIBERTY STREET from 107’ WEST OF RUTH ST to 1,135’ EAST
LONGFELLOW ST from E RIVER RD SVC RD to CUL-DE-SAC ST
RUTH STREET from LIBERTY STREET to RUTH CIRCLE
3. That the work be incorporated in the 2020 STREET REHABILITATION PROJECT
NO. ST2020–01.
4. That the work be performed under this project may be performed under one or more
contracts as may be deemed advisable upon receipt of bids.
5. That the Director of Public Works, James P. Kosluchar, P.E., is hereby designated as
the engineer for this improvement. He shall oversee the preparation of plans,
specifications and estimates of costs thereof for making of such improvements.
6. That final plans, specifications, and estimates are prepared by the Public Works
Engineering Division and provided to the City Council as they are completed.
7. That the Engineering Division call for bids in order that project award and
construction can be considered.
PASSED AND ADOPTED BY THE CITY COUNCIL OF THE CITY OF FRIDLEY THIS
TH
25DAY OF NOVEMBER 2019.
______________________________
SCOTT J. LUND - MAYOR
ATTEST:
__________________________________
DANIEL TIENTER - CITY CLERK