Resolution No. 2021-69 Locke Park Water Final Change Order
Resolution No. 2021-69
Approving Change Order No. 3 (Final) for Locke Park Water Treatment Plant
Improvement Project No. 17-509
Whereas, the Locke Park Water Treatment Plant Improvement Project No. 17-509 (Project)
included as part of the City’s Capital Investment Program is for improving the reliability of plant
filter operation, improved treatment of a public water supply, filter backwash water re-use, and
other ancillary items under contract with Magney Construction, Inc. of Chanhassen, MN
(Contractor); and
Whereas, the Project was funded by the City of Fridley’s Water Utility Fund through a Community
Investment Fund loan; and
Whereas, additional work has been directed by the City of Fridley (City) to be completed by the
Contractor including the Final Change Order No. 3 in the amount of $3,866.44; and
Whereas, cumulative additional work has been directed by the City has modified the original
contract from $3,349,000 to $3,398,377.22 (1.47% increase); and
Whereas, the Contractor performed work as directed by City staff and work is complete and
awaiting final payment.
Now, therefore be it resolved, that the City Council of the City of Fridley hereby approves
Approval of Change Order No. 3 (Final) for the Locke Park Water Treatment Plant Project in the
amount of $3,866.44.
rd
Passed and adopted by the City Council of the City of Fridley this 23 day of August, 2021.
_______________________________________
Scott J. Lund – Mayor
Attest:
Daniel Tienter – City Clerk