Resolution No. 2021-75 Final Change Order for Proj. No. 20-519
Resolution No. 2021-75
rd
Approving Change Order No. 1 (Final) for 53 Avenue Lift Station
Improvements Project No. 20-519
Whereas, the 53rd Avenue Lift Station Improvements Project No. 20-519 (Project) included as
part of the City’s Capital Investment Program is for relocating and improving the reliability of the
aging lift station; and
Whereas, the Project is under contract with Pember Companies, Inc. of Menomonie, WI
(Contractor); and
Whereas, the Project was funded by the City of Fridley’s Sanitary Sewer Utility Fund; and
Whereas, additional work has been directed by the City of Fridley to be completed by the
Contractor including the Final Change Order No. 1 in the amount of $5,304; and
Whereas, cumulative additional work has been directed by the City of Fridley has modified the
original contract from $726,807.50 to $732,111.50 (0.73% increase); and
Whereas, the Contractor performed work as directed by City staff and work is complete and
awaiting final payment.
Now, therefore be it resolved, that the City Council of the City of Fridley hereby approves
rd
Approval of Change Order No. 1 (Final) for the 53 Avenue Lift Station Improvements Project No.
20-519 in the amount of $5,304.
th
Passed and adopted by the City Council of the City of Fridley this 13 day of September,
2021.
_______________________________________
Scott J. Lund – Mayor
Attest:
Melisa Moore – City Clerk