Resolution No. 2021-100 Final Change Order-Village Green Project
Resolution No. 2021-100
Approving Change Order No. 1 Village Green Basin Expansion Project No. 603-60-15-475
Whereas, a contract with New Look Contracting (Contractor) for the Village Green Basin
Expansion, Project No. 603-60-15-475, was approved by the Fridley City Council on December 14,
2021; and
Whereas, the Project is funded through multiple grants and sources including: $50,000 from the
property owner, Dominium; $100,000 from a Metropolitan Council Grant previously approved by
the Fridley City Council; $100,000 from the Rice Creek Watershed District 2020 Urban Stormwater
Remediation Cost-Share Program; and approximately $50,000 from the City of Fridley (City); and
Whereas, additional work has been directed by the City to be completed by the Contractor
including Final Change Order No. 1 in the amount of $34,253.51; and
Whereas, cumulative additional work has been directed by the City has modified the original
contract from $275,068 to $309,351.51 (a 12.5% increase); and
Whereas, the Contractor performed work as directed by City staff and work is complete and the
project is near final completion.
Now, therefore be it resolved, that the City Council of the City of Fridley hereby approves
Approval of Change Order No. 1 for the Village Green Basin Expansion Project No. 603-60-15-475
in the amount of $34,253.51.
th
Passed and adopted by the City Council of the City of Fridley this 25 day of October, 2021.
_______________________________________
Scott J. Lund – Mayor
Attest:
Melissa Moore – City Clerk