Resolution No. 2023-128, Award 61st Avenue Parklet Project
Resolution No. 2023-128
st
Award 61 Avenue Parklet Project
st
Whereas, the construction of certain improvements identified as the 61 Avenue Parklet Project
(Project) is deemed to be in the interest of the City of Fridley (City) and residents of the City; and
Whereas, in 2019, 2020 and 2021 City staff conducted outreach to the affected community,
including holding meetings at the Civic Campus and onsite with the neighborhoods and
stakeholders to identify beneficial improvements of Trunk Highway 47; and
Whereas, the City has identified this park as a priority community development need serving a
low-moderate income community; and
Whereas, the City has received a Community Development Block Grant of $704,668 for the
Project; and
Now, therefore be it resolved, that the City Council of the City of Fridley hereby receives the
st
bids for the 61 Avenue Parklet Project per the attached bid tabulation (Exhibit A) and awards the
project to the lowest responsive bidder, Winberg Companies, LLC of Shafer, MN in the amount of
$466,674.85 which includes a 5% contingency, pending the City Engineer’s receipt and approval
of the Environmental Review and Funding Agreement with Anoka County.
rd
Passed and adopted by the City Council of the City of Fridley this 23 day of October, 2023.
_______________________________________
Scott J. Lund – Mayor
Attest:
Melissa Moore – City Clerk
Resolution No. 2023-128
Exhibit A
61stAvenueParkletProject
Owner:CityofFridley
BidOpening:10/6/202310:00AM
WinbergCompanies,LLCNewLookContracting,Inc.PetersonCompaniesMeyerContractingInc.ParkConstructionCompanyUrbanCompaniesParkstoneContracting,LLC
Line
Item
ItemDescriptionUnitQuantityUnitPriceExtensionUnitPriceExtensionUnitPriceExtensionUnitPriceExtensionUnitPriceExtensionUnitPriceExtensionUnitPriceExtension
1MOBILIZATIONLUMPSUM1$11,600.00$11,600.00$20,000.00$20,000.00$30,400.00$30,400.00$40,819.00$40,819.00$84,700.00$84,700.00$70,000.00$70,000.00$375,000.00$375,000.00
2CLEARINGLUMPSUM5$485.00$2,425.00$445.00$2,225.00$411.51$2,057.55$408.00$2,040.00$420.00$2,100.00$1,100.00$5,500.00$500.00$2,500.00
3GRUBBINGEACH5$485.00$2,425.00$300.00$1,500.00$411.51$2,057.55$272.00$1,360.00$280.00$1,400.00$300.00$1,500.00$350.00$1,750.00
4SALVAGESIGNEACH4$60.00$240.00$50.00$200.00$81.16$324.64$40.00$160.00$41.20$164.80$250.00$1,000.00$50.00$200.00
5REMOVECASTINGEACH2$200.00$400.00$250.00$500.00$162.33$324.66$198.59$397.18$236.00$472.00$500.00$1,000.00$400.00$800.00
6REMOVEREMOVEDRAINAGESTRUCTUREEACH2$585.00$1,170.00$1,000.00$2,000.00$505.79$1,011.58$791.82$1,583.64$926.00$1,852.00$2,500.00$5,000.00$1,500.00$3,000.00
7REMOVEPIPESEWERSEACH60$15.00$900.00$40.00$2,400.00$16.86$1,011.60$30.04$1,802.40$39.10$2,346.00$40.00$2,400.00$25.00$1,500.00
8SAWINGBITPAVEMENT(FULLDEPTH)EACH220$4.50$990.00$5.00$1,100.00$2.67$587.40$1.70$374.00$5.15$1,133.00$10.00$2,200.00$5.00$1,100.00
9SAWINGCONCRETEPAVEMENT(FULLDEPTH)EACH20$6.00$120.00$25.00$500.00$4.68$93.60$8.20$164.00$10.30$206.00$10.00$200.00$10.00$200.00
10REMOVECURBANDGUTTERLINFT230$12.00$2,760.00$8.00$1,840.00$4.29$986.70$11.40$2,622.00$8.35$1,920.50$12.00$2,760.00$5.00$1,150.00
11REMOVEBITUMINOUSPAVEMENTLINFT50$23.00$1,150.00$18.00$900.00$11.13$556.50$21.72$1,086.00$19.60$980.00$15.00$750.00$20.00$1,000.00
12REMOVECONCRETEPAVEMENTLINFT280$17.00$4,760.00$9.00$2,520.00$6.83$1,912.40$16.89$4,729.20$10.90$3,052.00$15.00$4,200.00$10.00$2,800.00
13COMMONBORROW(CV)LINFT240$39.00$9,360.00$20.00$4,800.00$21.85$5,244.00$54.90$13,176.00$0.01$2.40$10.00$2,400.00$50.00$12,000.00
14EXCAVATIONCOMMON(EV)LINFT526$48.00$25,248.00$13.00$6,838.00$51.77$27,231.02$53.05$27,904.30$25.50$13,413.00$60.00$31,560.00$30.00$15,780.00
15COMMONEMBANKMENT(CV)SQYD388$39.00$15,132.00$13.00$5,044.00$75.09$29,134.92$13.10$5,082.80$50.50$19,594.00$10.00$3,880.00$30.00$11,640.00
16STREETSWEEPER(WITHPICKUPBROOM)SQYD5$145.00$725.00$1.00$5.00$187.05$935.25$175.00$875.00$206.00$1,030.00$200.00$1,000.00$225.00$1,125.00
17AGGREGATEBASE(CV)CLASS5SQYD215$59.00$12,685.00$50.00$10,750.00$38.42$8,260.30$111.71$24,017.65$57.60$12,384.00$65.00$13,975.00$60.00$12,900.00
18BITUMINOUSPATCHSPECIAL(ROADWAY)SQYD50$142.00$7,100.00$90.00$4,500.00$86.00$4,300.00$93.50$4,675.00$115.00$5,750.00$90.00$4,500.00$95.00$4,750.00
19TYPESP9.5WEARINGCOURSEMIX(2,C)(TRAIL)CUYD25$395.00$9,875.00$300.00$7,500.00$166.63$4,165.75$298.50$7,462.50$203.00$5,075.00$175.00$4,375.00$225.00$5,625.00
20CASTINPLACEBENCHSWINGCONCRETEPIERCUYD8$858.00$6,864.00$1,665.00$13,320.00$1,640.00$13,120.00$2,277.18$18,217.44$2,060.00$16,480.00$1,200.00$9,600.00$1,725.00$13,800.00
21CASTINPLACELIGHTFIXTURECONCRETEPIERCUYD4$1,564.12$6,256.48$1,800.00$7,200.00$975.00$3,900.00$1,100.00$4,400.00$1,550.00$6,200.00$1,750.00$7,000.00$1,725.00$6,900.00
22CASTINPLACESOLARBOLLARDCONCRETEPADRDST20$487.91$9,758.20$665.00$13,300.00$545.00$10,900.00$250.00$5,000.00$567.00$11,340.00$600.00$12,000.00$575.00$11,500.00
23CASTINPLACETREEBOXHOUR3$3,625.00$10,875.00$7,500.00$22,500.00$2,445.09$7,335.27$7,128.61$21,385.83$8,420.00$25,260.00$5,000.00$15,000.00$9,000.00$27,000.00
24CASTINPLACERUNNELCUYD45$245.00$11,025.00$350.00$15,750.00$246.07$11,073.15$596.36$26,836.20$402.00$18,090.00$300.00$13,500.00$450.00$20,250.00
254"PVCPIPEDRAINSQYD62$35.00$2,170.00$100.00$6,200.00$24.38$1,511.56$55.23$3,424.26$60.80$3,769.60$40.00$2,480.00$40.00$2,480.00
26CONNECTTOEXISTINGSTORMSEWERSQYD2$1,525.00$3,050.00$850.00$1,700.00$1,129.56$2,259.12$4,240.35$8,480.70$1,780.00$3,560.00$2,000.00$4,000.00$2,000.00$4,000.00
27IRRIGATIONSYSTEMSQYD1$7,144.33$7,144.33$20,000.00$20,000.00$14,060.00$14,060.00$18,164.00$18,164.00$14,500.00$14,500.00$40,000.00$40,000.00$25,000.00$25,000.00
28CONNECTTOEXISTINGWATERMAINLINFT2$2,875.00$5,750.00$850.00$1,700.00$1,004.05$2,008.10$654.50$1,309.00$3,270.00$6,540.00$4,000.00$8,000.00$5,000.00$10,000.00
291"CORPORATIONSTOPGALLONS2$985.00$1,970.00$1,000.00$2,000.00$657.36$1,314.72$860.84$1,721.68$1,140.00$2,280.00$1,000.00$2,000.00$1,000.00$2,000.00
301"SADDLESQYD2$685.00$1,370.00$300.00$600.00$1,408.25$2,816.50$1,252.56$2,505.12$2,600.00$5,200.00$1,000.00$2,000.00$1,000.00$2,000.00
311"TYPEPEPIPETON25$120.00$3,000.00$55.00$1,375.00$48.38$1,209.50$108.40$2,710.00$170.00$4,250.00$50.00$1,250.00$50.00$1,250.00
321"CURBSTOPANDBOXTON2$1,385.00$2,770.00$825.00$1,650.00$1,222.28$2,444.56$1,526.65$3,053.30$1,280.00$2,560.00$2,000.00$4,000.00$1,500.00$3,000.00
33BLOWOUTVALVEASSEMBLYTON2$985.00$1,970.00$1,000.00$2,000.00$1,721.08$3,442.16$1,780.95$3,561.90$304.00$608.00$2,000.00$4,000.00$1,000.00$2,000.00
34CASTINGASSEMBLYLINFT1$945.00$945.00$1,000.00$1,000.00$972.88$972.88$1,189.26$1,189.26$987.00$987.00$1,000.00$1,000.00$2,500.00$2,500.00
35CONSTRUCTDRAINAGESTRUCTUREDES484020EACH6$1,124.00$6,744.00$1,225.00$7,350.00$988.73$5,932.38$1,392.62$8,355.72$1,240.00$7,440.00$1,500.00$9,000.00$1,100.00$6,600.00
36LANDSCAPEBOULDERSEACH8$439.25$3,514.00$950.00$7,600.00$901.13$7,209.04$403.00$3,224.00$928.00$7,424.00$500.00$4,000.00$450.00$3,600.00
374"CONCRETEWALKEACH6600$10.60$69,960.00$10.75$70,950.00$13.99$92,334.00$11.25$74,250.00$13.40$88,440.00$20.00$132,000.00$29.00$191,400.00
386"CONCRETEWALKEACH700$16.50$11,550.00$14.00$9,800.00$21.06$14,742.00$14.75$10,325.00$18.50$12,950.00$25.00$17,500.00$35.00$24,500.00
39CONCRETECURBANDGUTTERDESIGNB618EACH220$85.00$18,700.00$100.00$22,000.00$58.29$12,823.80$80.50$17,710.00$56.70$12,474.00$100.00$22,000.00$115.00$25,300.00
40PRECASTPAVEREACH1450$29.33$42,528.50$24.50$35,525.00$21.18$30,711.00$22.75$32,987.50$21.80$31,610.00$28.00$40,600.00$25.00$36,250.00
412"NONMETTALICCONDUIT(WITHPULLSTRING)LINFT130$28.68$3,728.40$20.00$2,600.00$12.07$1,569.10$24.00$3,120.00$16.50$2,145.00$18.00$2,340.00$20.00$2,600.00
42TRUNCATEDDOMESLINFT110$73.00$8,030.00$76.00$8,360.00$151.63$16,679.30$79.00$8,690.00$63.90$7,029.00$80.00$8,800.00$75.00$8,250.00
43TRAFFICCONTROLLINFT1$2,700.00$2,700.00$2,500.00$2,500.00$3,741.00$3,741.00$2,250.00$2,250.00$2,320.00$2,320.00$1,000.00$1,000.00$5,000.00$5,000.00
44INSTALLSIGNLINFT4$350.00$1,400.00$300.00$1,200.00$155.00$620.00$275.00$1,100.00$283.00$1,132.00$250.00$1,000.00$300.00$1,200.00
45CONIFEROUSTREE6'HTB&BLINFT10$695.13$6,951.30$830.00$8,300.00$558.28$5,582.80$506.00$5,060.00$575.00$5,750.00$500.00$5,000.00$560.00$5,600.00
46DECIDUOUSTREE6'HTB&BLINFT27$624.04$16,849.08$685.00$18,495.00$501.87$13,550.49$516.50$13,945.50$517.00$13,959.00$600.00$16,200.00$575.00$15,525.00
47DECIDUOUSSHRUB2'HTBRPOUND76$107.00$8,132.00$105.00$7,980.00$50.80$3,860.80$95.00$7,220.00$52.30$3,974.80$100.00$7,600.00$105.00$7,980.00
48STABILIZEDCONSTRUCTIONEXITEACH1$2,452.00$2,452.00$1.00$1.00$2,687.50$2,687.50$2,736.00$2,736.00$3,770.00$3,770.00$3,000.00$3,000.00$4,000.00$4,000.00
49STORMDRAININLETPROTECTIONEACH10$185.00$1,850.00$175.00$1,750.00$161.25$1,612.50$283.50$2,835.00$200.00$2,000.00$350.00$3,500.00$225.00$2,250.00
50SEDIMENTCONTROLLOGTYPEWOODFIBEREACH500$4.00$2,000.00$6.50$3,250.00$5.59$2,795.00$4.10$2,050.00$5.15$2,575.00$10.00$5,000.00$7.00$3,500.00
51FERTILIZERTYPE3EACH300$3.00$900.00$2.50$750.00$0.60$180.00$3.10$930.00$0.62$186.00$3.00$900.00$3.50$1,050.00
52COMMONTOPSOILBORROWSQFT80$58.00$4,640.00$60.00$4,800.00$42.24$3,379.20$66.16$5,292.80$54.30$4,344.00$50.00$4,000.00$100.00$8,000.00
53ROLLEDEROSIONPREVENTIONCATEGORY25LINFT800$4.75$3,800.00$5.00$4,000.00$2.40$1,920.00$3.10$2,480.00$2.45$1,960.00$3.00$2,400.00$3.50$2,800.00
54SODDINGTYPELAWNLINFT610$6.00$3,660.00$15.00$9,150.00$11.10$6,771.00$7.20$4,392.00$11.40$6,954.00$10.00$6,100.00$8.00$4,880.00
55SEEDINGLINFT1$1,650.00$1,650.00$2,000.00$2,000.00$10,686.00$10,686.00$2,479.00$2,479.00$11,000.00$11,000.00$15,000.00$15,000.00$3,000.00$3,000.00
56MULCHMATERIALTYPE6SQYD30$130.00$3,900.00$135.00$4,050.00$93.77$2,813.10$155.00$4,650.00$96.60$2,898.00$75.00$2,250.00$105.00$3,150.00
57SEEDMIXTURE21111SQYD100$4.00$400.00$4.00$400.00$0.87$87.00$1.10$110.00$0.90$90.00$6.00$600.00$1.25$125.00
58SEEDMIXTURE25131SQFT330$6.00$1,980.00$12.00$3,960.00$3.62$1,194.60$6.00$1,980.00$3.75$1,237.50$6.00$1,980.00$6.50$2,145.00
59SEEDMIXTURE35241LUMPSUM37$25.00$925.00$60.00$2,220.00$25.95$960.15$30.00$1,110.00$26.70$987.90$15.00$555.00$33.00$1,221.00
60HYDRAULICBONDEDFIBERMATRIXEACH3500$1.25$4,375.00$1.50$5,250.00$1.79$6,265.00$1.00$3,500.00$1.85$6,475.00$1.50$5,250.00$1.15$4,025.00
61MULCHMATERIALTYPE1LUMPSUM5$1,000.00$5,000.00$300.00$1,500.00$474.80$2,374.00$930.00$4,650.00$490.00$2,450.00$500.00$2,500.00$1,000.00$5,000.00
62INSTALLBIKERACKEACH2$565.00$1,130.00$350.00$700.00$415.00$830.00$579.50$1,159.00$412.00$824.00$500.00$1,000.00$200.00$400.00
63INSTALLSOLARBOLLARDSQFT20$364.27$7,285.40$350.00$7,000.00$305.00$6,100.00$200.00$4,000.00$288.00$5,760.00$320.00$6,400.00$325.00$6,500.00
64INSTALLLIGHTFIXTUREEACH4$855.37$3,421.48$1,000.00$4,000.00$815.00$3,260.00$700.00$2,800.00$876.00$3,504.00$1,000.00$4,000.00$1,000.00$4,000.00
65INSTALLDRINKINGFOUNTAINSYSTEM1$650.00$650.00$3,650.00$3,650.00$1,900.00$1,900.00$2,662.00$2,662.00$5,150.00$5,150.00$25,000.00$25,000.00$6,000.00$6,000.00
66INSTALLRECEPTACLEEACH2$285.00$570.00$350.00$700.00$400.00$800.00$440.00$880.00$443.00$886.00$250.00$500.00$265.00$530.00
67INSTALLBIKELOCKERSEACH3$495.00$1,485.00$1,000.00$3,000.00$1,085.00$3,255.00$1,516.00$4,548.00$1,180.00$3,540.00$1,000.00$3,000.00$800.00$2,400.00
68INSTALLSOLARBENCHCUYD1$2,200.00$2,200.00$2,250.00$2,250.00$2,130.00$2,130.00$2,800.00$2,800.00$2,010.00$2,010.00$2,200.00$2,200.00$2,250.00$2,250.00
69INSTALLBENCHPOUND6$405.00$2,430.00$350.00$2,100.00$460.00$2,760.00$1,516.00$9,096.00$600.00$3,600.00$500.00$3,000.00$300.00$1,800.00
70INSTALLBENCHSWINGACRE4$505.00$2,020.00$2,250.00$9,000.00$2,980.00$11,920.00$4,178.00$16,712.00$2,060.00$8,240.00$2,000.00$8,000.00$750.00$3,000.00
71INSTALLBIKESTATIONPOUND1$958.00$958.00$1,150.00$1,150.00$960.00$960.00$1,344.00$1,344.00$1,030.00$1,030.00$500.00$500.00$1,200.00$1,200.00
BidTotal:$444,452.17$464,708.00$485,958.70$535,722.88$557,318.50$657,705.00$995,531.00