Resolution No. 2024-93, Approving Change Order No. 3 (Final) for 53rd Avenue Trail and Walk Improvements Project No. ST2023-21
Resolution No. 2024-93
rd
Approving Change Order No. 3 (Final) for 53 Avenue Trail and Walk Improvements
Project No. ST2023-21
Whereas, the 53rd Avenue Trail and Improvements Project (Project) included street rehabilitation on
53rd Avenue from Main Street to Trunk Highway 65 (Central Avenue), installation of a new
bituminous trail on the south side of 53rd Avenue from Main Street (CSAH 102) to Central Avenue
(Trunk Highway 65), and installation of a concrete sidewalk on the north side of 53rd Avenue from
Trunk Highway 47 (University Avenue) to Monroe Street as part of the City of Fridley’s (City) regular
street maintenance program under a contract with Park Construction Company of Spring Lake Park,
MN (the Contractor); and
Whereas, the Project was funded by MnDOT’s Local Road Improvement Program (LRIP) grant, the
City of Columbia Heights through a cost-share project Joint Powers Agreement, the City’s Minnesota
State Aid System funding, utility enterprise funds and special assessments; and
Whereas, City staff directed the Contractor to perform work for the items that are incorporated into
this change order as enumerated in the agenda report; and
Whereas, work under this change order would increase the contract by $28,479.40, or 1.3%; and
Whereas, cumulative additional work has been directed by the City that modified the contract from
$1,776,297.26 to $2,198,486.19 (a 23.8% increase) to meet the goals and requirements of the project.
Now, therefore be it resolved, that the City Council of the City of Fridley hereby approves Approval
rd
of Change Order No. 3 (Final) for the 53 Avenue Trail and Improvements Project ST2023-21 in the
amount of $28,479.40.
Passed and adopted by the City Council of the City of Fridley this 8th day of July, 2024.
_______________________________________
Scott J. Lund – Mayor
Attest:
Melissa Moore – City Clerk