Resolution No. 2024-145, Approve Change Order No. 1 for 2024 Neighborhood Parks Improvement Project No. 24-70457
Resolution No. 2024-145
Approve Change Order No. 1 for
2024 Neighborhood Parks Improvements Project No. 24-70457
Whereas, the 2024 Neighborhood Parks Improvements Project No. 24-70457 (Project) includes
removals, grading, concrete curb & walkways, sport courts, fencing, shelters, miscellaneous site
amenities, and restoration at Edgewater Gardens Park, Plymouth Square Park, and Logan Park
performed under contract with Peterson Companies, Inc. of Chisago City, MN (Contractor); and
Whereas, on April 25, 2022, the Council adopted Resolution No. 2022-36, which approved the
Park System Improvement Plan Final Report and authorizes staff to begin the implementation
phase of the Plan; and
Whereas, the Park System Improvement Plan provides funding for its implementation and
includes site improvements in Edgewater Gardens Park, Plymouth Square Park, and Logan Park;
and
Whereas, additional work has been directed by the City to be completed by the Contractor
including the Change Order No. 1 in the amount of $105,067.60; and
Whereas, cumulative additional work was directed by the City that modified the original contract
from $725,600.74 to $830,668.34 (14.5% increase); and
Now, therefore be it resolved, that the City Council of the City of Fridley hereby approves
Change Order No. 1 for the 2024 Neighborhood Parks Improvements Project in the amount of
$105,067.60.
th
Passed and adopted by the City Council of the City of Fridley this 14 day of October, 2024.
_______________________________________
Scott J. Lund – Mayor
Attest:
Melissa Moore – City Clerk